The workbook currently contains two valid-looking art figures that answer different questions. They are not yet reconciled.
Short Handoff Statement
The detailed Estimator itemizes all currently modeled 3D-art work at $2,289,686. The buyer-facing Cost tab carries only $1,212,216 in its five direct route/vehicle art rows. The $1,077,470 difference is not confirmed savings; it is art scope omitted from, or reallocated outside, those five rows. Before reducing the proposal price, the team must either place these assets elsewhere in the Cost tab or explicitly remove their scope and update both sheets.
Detailed Estimator
$2,289,686
All listed train and route 3D modeling
Cost-Tab Art Rows
$1,212,216
Five buyer-facing route/vehicle rows
Unreconciled Gap
$1,077,470
Not an approved reduction
| Art scope behind the gap | Current estimator value |
|---|---|
| Mid/far-field environment across 50 miles | $537,485 |
| 40 mid-field points of interest / landmarks | $284,992 |
| 29 miles of near-field route-extension geometry | $206,619 |
| Low-fidelity train-car shell set | $26,874 |
| S70-versus-S700 visual differences | $21,499 |
| Parent-row rounding reconciliation | $1 |
| Total unreconciled art scope | $1,077,470 |
Required decision: Keep and reallocate each line, reduce its quantity/fidelity, or remove it with matching scope language. Do not simply subtract $1.08M while leaving the promised environment unchanged.